Woodville Combined Sewer Separation
Woodville Combined Sewer Separation Design Start-up Meeting Minutes from 3/31/2008

1.  Current Status of Project:  Field topography of all three Phases should be complete this  
     week, weather permitting.  Plan and profile sheets of topography plotted for Phase 1 and
     Phase 2.  System design to begin within 1 to 2 months after topography can be reviewed
     by Village (for existing water main locations ) and PDG (for field pick-up shorts).

2.  Current Project Schedule (as submitted for STAG application):

          -  Topography and Design, 12/2007 - 12/2008
          -  OPWC Grant Agreement anticipated to be provided for Village acceptance
             and/or execution, 7/2008
          -  Advertise for Bid, 1/2009 - 2/2009
          -  Construct Sewer Mains, 3/2009 - 12/2009
          -  Existing Service Lateral Connections (if by property owners), 4/2009 - 12/2010
          -  Closure of Existing CSO's: could be on-going until 12/2010+

3.  Optional additions to Project for the Village to consider (need decisions by the end of
     May 2008):

          a.  New service lateral installations are currently planned to be installed to the street
               right-of-way line for each parcel fronting on the project (cost is included in
               current Probably Project Cost).  New service lateral installation from right-of-way
               to structure being served to be completed by the property owner at their cost.
               Will Village want to include the latter installation as part of the project (additional
               project cost estimated at $1.5 Million engineering services)?

                    -  if included Village may need temporary access easement from each
                       property owner
                    -  if not included CSO's must remain open until all service connections are
                       completed in each area served by a CSO
                    -  if not included, CSO closure may need to be completed by another
                       contractor and/or project

          b.  Will Village be proceeding with the construction of all three phases as one
               project, and if so, does the Village prefer to bid as one contract, or as three
               more contracts?

               This may allow more (smaller) contractors to bid individual contracts (one for
               each phase) and produce better bid prices.  Construction could be expedited if
               three contractors attack the project during the same time period.

          c.  Village could include pump station upgrades/renovations and/or other
               equipment as part of the Project at an additional cost.  This could include,
               pump/control replacements, permanent or portable standby power upgrades/
               equipment, telemetry equipment, sewer flushing/vacuum truck, sewer
               televising equipment, etc.

               Probable additional project cost not yet determined.

          d.  Village may want to discontinue gravity sanitary sewer to existing basements
               which could result in shallower gravity sewer installations.  PDG recommended
               village complete "basement survery" as part of other Village predesign/
               preconstruction inspection work.

               Discussed having current Village meter reader expand work hours to do
               inspections/basement survey, or hire college engineering/construct tech
               student on temporary basis to do this work (summer, nights, weekends, etc)

          e.  Include existing catch basin and/or manhole replacement, repairs or
               rehabilitation throughout Village's existing storm sewer and combination sewer
               system.  This will be additional cost to the project.

4.  PDG to provide clarification/details of current contract scope which includes
     topographic work and design of all three phases, as well as bidding of Phase 1 only.

     PDG contract amendment will eventually be necessary to include Phase 2 and 3 in
     bidding work, and Construction Services for all three phases if constructed as one
     project or simultaneously.

5.  Anticipated Village responsibilities during design and construction:

          a.  Subsurface soil investigation for depth to rock (complete in-house with digger
               truck)

          b.  Televise existing sewer system where determined necessary (DEFA may be
               requiring this as well, PDF to confirm)

          c.  Existing service lateral investigation to determine locations, depth, redirect
               inside structure, storm/sanitary service separation, etc.  May require smoke
               testing, dye testing, service televivsing

          d.  Be available during construction as needed for existing utility identification,
               repair of damaged water service laterals, mains, etc. as well as to approve
               necessary changes during construction due to unknown main utility line conflicts
               found.

          e.  Continue to keep community informed of project status as design phase
               progresses.  Provide weekly progress/schedule updates through local newspaper
               during construction.  PDG and Contractor to provide info to Village.

          f.  Enforce and oversee installation and inspection of new service lateral installations/
               structure connections for each property.

6.  Status of Grants/Loans:

                    -  OPWC Grant applied for and informally approved - $175,000 grant for
                       Phase 1
                    -  State and Tribal Assistance Grant (STAG) applied for, should hear if
                       successful in Oct/Nov 2008 with being available 1/2009 - applied for
                       $1,000,000 grant, 25% Village match
                    -  DEFA 0% Loan informally approved for Phase 1, PDG checking to see
                       if DEFA will allow all three projects to be eligible for 0% loan constructed
                       as one project or simultaneously.  If so Village may need to re-nominate
                       project for DEFA loan for 2009 construction.
                    -  Village should be applying for State "White Paper Money" soon.  PDG
                       to follow-up on this and begin preperation of request.

7.  There may be some environmental issues to deal with (OEPA, ODNR, Army Corps of
     Engineers) particularly with regard to CSO closures/Portgage River.  PDG to investigate
     requirements further and advise Village of findings.

8.  Village to consult with Sollicitor regarding need for easements (blanket or specific) for
     individual properties if all service lateral connections are included in the Village's project.
     Also review need for new ordinance for service connections to new sanitary sewer system.

9.  PDG suggested further committee update meetings as project moves forward with next
     meeting anticipated in June or July 2008.